Food & Beverage

朱光玉火锅馆 — Four Outlets in KL, Selangor and Johor, Every Opening Date Held

Four hotpot outlets across Kuala Lumpur, Selangor and Johor, zoned for a dining room where every table is a live heat source.

Client

朱光玉火锅馆 (Zhu Guang Yu Hot Pot) — a leading Chinese hotpot brand, expanding into Malaysia through a Malaysian holding partner.

Challenge

Hotpot is the most demanding comfort environment in commercial F&B. Every table is a live heat source: induction or gas burners running continuously beneath diners, plus steam, plus a full commercial kitchen behind.

Cooling that fights a dining room full of active burners is not a floor-area calculation — it is a heat load problem where getting the zoning wrong produces a dining hall that is simultaneously too cold at the perimeter and unbearable at the centre.

Compounding it: a brand rolling out multiple outlets nationally needs the same guest experience in every location, in buildings that differ completely in shape, ceiling height, and services access — and every outlet has a fixed opening date.

Solution

CASS was appointed HVAC design-and-build contractor across the brand's Malaysian outlet programme, delivering four outlets in Kuala Lumpur (Pudu), Klang (Selangor) and Johor Bahru (Johor).

System design was zoned by function rather than applied uniformly — higher-capacity ceiling cassettes over dining halls carrying the burner load, separate units per VIP and private dining room for independent control, dedicated provision for kitchen, canteen, dishwash and cold-store areas, and wall-mounted units where cassette installation was not appropriate.

Execution

Each outlet was delivered to the brand's opening schedule, with scope covering equipment supply, installation, copper piping and SIRIM-certified control wiring, insulated condensate drainage, and cable tray systems. Variation orders were absorbed mid-project as layouts evolved — outdoor dining areas, additional dining zones, store rooms, and dishwash areas added without displacing the opening date.

The Johor Bahru outlet was executed as an outstation deployment: crews accommodated on site for the duration, crane and lifting equipment mobilised, and the full installation completed away from the Klang Valley base.

Evidence

  • Four outlets delivered across KL, Selangor and Johor
  • Multi-outlet programme sustained from 2025 into 2026
  • Zoned system design per outlet: dining halls, VIP rooms, kitchen, canteen, cold store
  • Outstation delivery capability proven — crews, accommodation, crane, full install
  • Mid-project variation orders absorbed without moving opening dates
  • Daikin equipment throughout, as an Authorised Daikin Dealer

Outcome

A repeat outlet-rollout relationship: once the first outlet's system design was proven, subsequent openings became execution problems rather than design problems — which is what allows a multi-outlet operator to hold opening dates.

On site

  • The 朱光玉火锅馆 outlet on Jalan Pudu, Kuala Lumpur, lit at night.
    Kuala Lumpur (Pudu) outlet
  • The 朱光玉火锅馆 outlet in Klang, Selangor, seen from the forecourt.
    Klang, Selangor outlet
  • The 朱光玉火锅馆 outlet in Johor Bahru at night, under its illuminated frontage.
    Johor Bahru outlet — delivered as an outstation deployment
  • A ceiling cassette mounted into a coffered ceiling during fit-out, still in its factory wrapping.
    Pudu, during fit-out — cassette set into the ceiling coffer, insulated drainage and cable tray run above
  • A ceiling cassette suspended from the structural slab with ducting and drainage routed to it.
    Pudu, during fit-out — unit hung off the slab before the ceiling closes
  • A wrapped ceiling cassette in position among ceiling framing and services.
    Pudu, during fit-out — dining-hall unit in position among the ceiling framing
  • A shophouse rear elevation carrying rows of outdoor condensing units on wall brackets across several storeys.
    Pudu — outdoor plant ranked up the rear elevation
  • A ceiling cassette still in its protective wrapping, fitted above a dining room during fit-out.
    Cassette in and wrapped, ahead of the ceiling closing
  • A finished dining room with a ceiling cassette set into the ceiling above the seating.
    The finished dining room — capacity set against the burner load beneath
  • A VIP dining room with its own ceiling cassette, independently controlled.
    VIP room on independent control, per the zoning strategy

This project was delivered under HVAC Design & Build.